Here are the key steps to using our Calculator:
The user inputs 3 values:
Actual Cost (AC) - the actual cost spent so far
Earned Value (EV) - the budgeted cost of completed work
Planned Value (PV) - the budgeted cost of planned work
When the user clicks "Calculate", JavaScript functions are triggered to perform calculations:
Estimate to Complete (ETC) is calculated by: ETC = EV - AC
Schedule Performance Index (SPI) is calculated by: SPI = EV / PV
Estimate at Completion (EAC) is calculated by: EAC = AC + ETC / SPI
The ETC, SPI, and EAC results are displayed on the page dynamically using JavaScript to insert the values.
This allows the user to input data, click a button, and see key Earned Value metrics calculated instantly to evaluate project performance.
Get in touch
Address
Mapping Crimes Inc.
1000 Highland Colony Pkwy Building 5000, Suite 5203, Ridgeland, MS 39157
Contacts
769-206-0978
dlewis@lewisautomatedbusinessconsulting.comconsulting.com